HDB BTO · Tengah · West region
Plantation Dew Renovation & Interior Design
Plantation Dew is an HDB BTO project in Tengah, listed in the November 2026 BTO exercise with 710 flats, as recorded from HDB’s BTO portal in our project file. That official confirmation covers the launch and the unit count only. TOP and key-collection dates are unconfirmed. Tenure is left blank. Use your HDB documents for typologies, and do not treat a portal launch as a handover date. This page sets out what is on file and how to plan your Plantation Dew renovation.
Plantation Dew at a glance
- Type
- HDB BTO
- Developer
- HDB
- Launch / TOP / key date
- November 2026 launch. The official confirmation in our file covers the launch date only, not TOP or key collection
- Area
- Tengah
- Region
- West
- Units
- 710
Facts from the sources listed at the end of this page.
Planning your Plantation Dew interior
A newly launched Tengah BTO is still years from renovation, which is useful in a town that is itself still being built out. When HDB issues your approved plan, the interior brief that usually pays off is built-in: a fitted kitchen with a tall pantry or fridge run, full-height wardrobes, an entry cabinet, and a living-room joinery wall, with a built-in desk if a common bedroom will be a study. Maison specifies this as custom carpentry, not as IKEA-style furniture. No official floor plan is on file, and we will not invent typologies or a typical Plantation Dew layout.
Brickland Weave and Plantation Edge I & II are unconfirmed near-completion pages in the same town and are not a guide to when Dew will get keys. Plantation Creek, Garden Waterfront I & II and Plantation Verge were packed earlier. We will not invent walking times to any present or future MRT station, and we will not assign a view from the project name.
Keep the official plan when it is issued, and write to us when you want the carpentry drawings frozen well before any permit is due. After keys, inspect defects and apply for the HDB renovation permit before fabrication. A moderate carpentry scope is often planned at about six to ten weeks on site after approvals — an editorial allowance, not a promise. WhatsApp Maison with your unit type and plan when you have them. We are not affiliated with HDB.
Planning your Plantation Dew renovation
Defects check at handover
- Report defects within 30 days of key collection, before renovation starts (HDB move-in guide). The Defects Liability Period runs 1 year from key collection.
- Check floor and wall tiles for hollow or chipped pieces, plaster for cracks, and paint for stains.
- Test every door, window, lock, tap, floor trap, light point and power socket.
- Report through the QR code in your Welcome Kit or your project's Building Service Centre, with photos.
What the rules allow
- Use a contractor listed in HDB's Directory of Renovation Contractors; they can apply for the permit for you.
- A permit is needed for works such as removing floor finishes, raising floor levels in wet areas, or hacking or altering walls.
- For the first 3 years, toilet wall and floor finishes in a new BTO flat cannot be removed. New tiles can be overlaid.
- General works: Monday to Saturday, 9am to 6pm. Noisy works: Monday to Friday, 9am to 5pm. No works on Sundays or public holidays.
- Household shelter walls must not be hacked or drilled. Windows need a BCA-approved window contractor; air-conditioners need a BCA-trained installer.
Rules change, so we check the current version for your unit before we quote. Full bto key collection renovation guide
From keys to move-in
- 01
Before keys 4 to 8 weeks
Layout, 3D drawings and an itemised quotation, so work can start as soon as defects are reported.
- 02
Keys + first 2 weeks 1 to 2 weeks
Defects inspection and reporting, permit application, measurements on site.
- 03
Wet works and electrical 2 to 3 weeks
Tile overlays, screed or vinyl, wiring and plumbing points.
- 04
Carpentry 3 to 5 weeks
Built in the factory while wet works run on site, then installed.
- 05
Finishing 1 to 2 weeks
Painting, lights, glass, cleaning and a handover walk-through.
Plantation Dew renovation FAQ
When was Plantation Dew launched?
Our project file records: 2026-11 launch. That official confirmation covers the launch date only, not TOP or key collection.
Is the key-collection date for Plantation Dew confirmed?
No. Completion and keys are unconfirmed in our file. Use your HDB documents for your own appointment, when you have one.
Do you have the Plantation Dew floor plan?
No official floor-plan or site image is on file for this page, so none is published here. Please send your approved HDB unit plan.
What should I send Maison?
Your approved floor plan, unit type if you have it, and a key date if one is already in writing. After keys, an HDB renovation permit is required before works. WhatsApp us at https://wa.me/6593391185.
Sources
Facts checked against the sources on file, 11 November 2026.
Maison Interior Design is an independent interior design firm. We are not appointed by, or affiliated with, the developer, HDB or the building's owner. We have not worked at Plantation Dew unless our portfolio says so. Concept pictures are AI-generated style concepts, not photos of a finished unit.
Nearby new launches
Talk to Maison
Planning your Plantation Dew renovation?
WhatsApp Maison
WhatsApp Maison with your unit type, approved floor plan and key date (if you have one).